Rebar Bar Lists Explained: How to Read and Check One Before Fabrication

Bent rebar bundles tagged by bar mark from a rebar bar list
In this article

A rebar bar list is the table a fabricator uses to cut, bend, tag and ship reinforcing steel. For every bar mark it gives the bar size, quantity, shape, bending dimensions, total length and weight, grouped by element or pour. Outside the U.S. the same document is usually called a bar bending schedule (BBS).

The placing drawings tell the crew where the steel goes. The bar list tells the shop what to make. If the two disagree, the shop makes the wrong thing, and the crew finds out on the deck. Learning to read and check a bar list takes an hour and saves days.

Key takeaways

  • Every row of a rebar bar list is one bar mark: same size, shape and length.
  • Shapes follow standard CRSI shape codes, with letters for each bend dimension.
  • Lengths are cut lengths, which include the steel used in bends and hooks.
  • Lists are grouped by pour or element, so steel arrives in the order it is placed.
  • Checking a bar list against the placing drawings catches most errors before they reach the shop.

What a rebar bar list contains

ColumnWhat it means
Bar markUnique ID that links the list to the placing drawing and the tag on the bundle
SizeBar size, such as #4 or #8 in U.S. designation
Grade / coatingSteel grade and any epoxy coating or galvanizing
QuantityNumber of identical bars for that mark
Shape codeStandard shape, from a straight bar to a closed stirrup
Bending dimensionsLengths of each segment, labeled A, B, C and so on
Total lengthCut length of each bar before bending
WeightWeight per mark and total for the group
LocationElement, level or pour where the bars go

How to read a rebar bar list, step by step

  1. Start with the header. Check the project, the element or pour, the drawing reference and the revision.
  2. Match the bar mark to the placing drawing. Every mark on the drawing should appear on the list, and the other way around.
  3. Read the shape code and picture the bar. A straight bar has one dimension; a stirrup has several.
  4. Check the bending dimensions against the element size minus cover.
  5. Confirm the quantity using the spacing and the length of the element.
  6. Look at the weight. Totals by pour help the shop plan and help you check invoices.

Shape codes and bending dimensions

Standard shapes come from the CRSI Manual of Standard Practice. Each shape has a code and a sketch with lettered dimensions. Using standard shapes means any fabricator reads the list the same way, and bending machines can be set up quickly. Special shapes are drawn on the list with every dimension shown.

A useful habit: for any shape you have not seen before, sketch it at the side of the list with its dimensions. If it does not fit inside the concrete outline minus cover, something is wrong.

Why cut length is not the same as the drawn length

A bar bent into an L does not use the sum of its two legs. Bending around a pin stretches and shapes the steel, so the cut length is adjusted using the standard bend allowances. Hooks add length beyond the bend. A good rebar bar list already includes these allowances, so the shop cuts the right length the first time.

How bar lists are organized

The best lists follow the construction sequence. Footings for one area, then the walls above them, then the columns, then each slab pour. Bundles are tagged with the bar mark and location, so the crew can find what they need without opening every bundle on site. That sequence comes from the placing drawings, which we explain in our complete guide to rebar detailing.

A quick checklist before you approve a bar list

  • Every bar mark on the drawings appears on the list, with the same size.
  • Quantities match spacing and element length.
  • Bending dimensions fit the element minus cover.
  • Hooks and lap lengths match the project’s splice table.
  • Coated bars are flagged as coated.
  • Totals by pour make sense against the estimate.
  • The revision on the list matches the revision on the drawing.

Most of the problems we find in reviews are on this list. We cover the rest in mistakes that slip through rebar packages.

Bar lists from a 3D model

When reinforcement is modeled in 3D, bar lists come straight from the model. That removes copying errors between drawings and lists, and any change in the model updates the list automatically. It also makes it easier to compare quantities with the original rebar takeoff from the bid.

If you need bar lists prepared or checked, our team delivers bar lists and placing drawings for your next pour on U.S. business hours.

Frequently Asked Questions

What is the difference between a bar list and a bar bending schedule?

They are the same document. Bar list is the common U.S. term; bar bending schedule (BBS) is used in most other countries.

Who prepares the rebar bar list?

The rebar detailer, usually working for the reinforcing steel fabricator, prepares it together with the placing drawings.

Does the Engineer of Record approve bar lists?

The engineer reviews the placing drawings for conformance with the design. Bar lists are often submitted with them, but their accuracy remains the fabricator’s responsibility.

What does a bar mark mean?

A bar mark is a unique code for a group of identical bars. It links the placing drawing, the bar list and the tag on the bundle delivered to site.

Why is the cut length longer than the drawn bar?

Because bends and hooks use steel. The cut length includes standard allowances so the bar ends up with the right dimensions after bending.

Have a project?

Talk to a Grupo ADIPSA engineer

Tell us what you are building or what you need detailed, and we will reply with the scope and the next steps.

Keep reading

Related articles

Estimator preparing a rebar takeoff from structural drawings
Rebar Detailing

Rebar Takeoff Guide: How to Estimate Reinforcing Steel Quantities

How to do a rebar takeoff from structural drawings, with standard bar weights, a worked example and the items estimators most often
Slab rebar grid used as an example of a rebar takeoff
Rebar Detailing

9 Rebar Detailing Mistakes That Delay Pours (and How to Catch Them Early)

The rebar detailing mistakes we find most often in reviews, why they happen and a reusable checklist to catch them before the
Reinforcing bars overlapping at a rebar lap splice inside a wall form
Rebar Detailing

Rebar Lap Splices, Development Length and Hooks: A Practical Guide

How rebar lap splices, development length and standard hooks work, when to use couplers and how these criteria show up in rebar